Waiakoa Drainage Repair

Project Name


Waiakoa Drainage Repair
Job No. 11-20


Scope of Work


The project involves the demolition of the existing 48” and 24” pipe culverts crossing South Kihei Road associated structures. Construction of twin 10’ x 3’ concrete box culverts with concrete railings; clearing and grubbing; earthwork; placing of dumped riprap, reconstructing pavement areas; cold planning; and installation of guardrails, signage, pavement markings, and other incidental items.
(Project Map)
  

When


NTP:  July 24, 2017
Contract Working Days: 140
Anticipated Completion Date:  First week of March, 2018.
 

Streets Involved


South Kihei Road

Contractor


Hawaiian Dredging Construction Co.
P.O. Box 4088
Honolulu, Hawaii 96812

Contract Cost


$1,876,000


Project Contact


DPW Engineering Division (808) 270-7745.

 Project Update
Work Completed Week of 2/26/18 - 03/02/18
      -  Install guardrail.
      -  Asphalt pave from project to Uwapo Road.
      -  Install roadway striping and pavement markers.
      -  Install object markers.
      -  Asphalt pave under guardrails.  
      - Remove traffic detour signs.
      -  General cleanup and demobilization.
 Work Scheduled This Week (3/05/18 - 3/09/18):
      -  No work scheduled.
      -  Landscape installation pending.
       (Click on the link below for more info and picture.) 
Anticipated Completion Date
      -  South Kihei Road Opened for use afternoon of March 1.