Baldwin Avenue Pavement Rehabilitation, Phase 2

Project Name


Baldwin Avenue Pavement Rehabilitation, Phase 2
FAP Project No. STP-0390(002)


Scope of Work


The project includes pavement reconstruction of Baldwin Avenue between Hana Highway and Haliimaile Road with an asphalt concrete, asphalt treated base and aggregate base course pavement section. Other work includes cold planing and resurfacing of existing pavement, installation of pavement striping and markers, installation of signs, reconstruction of concrete sidewalk and other incidental work.
(Project Map)

When


NTP: March 8, 2017
Contract Working Days: 180


Streets Involved


Baldwin Avenue (Hana Hwy to Haliimaile Road)

Contractor


Hi-Built LLC
72 Ting's Drive
Wailuku, Hawaii 96793



Contract Cost


$3,980,409


Project Contact


DPW Engineering Division (808) 270-7445