Molokai Baseyard Improvements, Phase I

Project Name


Malokai Baseyard Facility
Project No. 14-32

Scope of Work


The new baseyard will consist of one Administrative Building, approximately 2,560 SF, one Maintenance Building, approximately 7,440 SF, and one Vehicle Storage Building, approximately 3,960 SF, located in Naiwa, Molakai.

When


NTP:  January 8, 2018
Contract Working Days:  550 / Amended Contract Days: 697
Original Completion Date:  July 12, 2019 / Revised Completion Date:  Dec. 6, 2019

Streets Involved


Pueo Place, off of Ulili Street

Contractor


F&H Construction
1728 Wili Pa Loop, Suite 200
Wailuku, HI 96793

Contract Cost


$7,528,000.00

Project Contact


County of Maui, Department of Public Works
Engineering Division
(808) 270-7745

Construction Update:



Work Completed Week of 09/01/19 - 09/07/19


  • Metal Roofing for Maint Bldg
  • Steel Framing for Maint Bldg
  • Roof on Veh Storage Bldg
  • Frame Bathroom for Veh Storage Bldg
  • Electrical/Mechanical Rough-in for Veh Storage

Work Scheduled Week of 09/08/19 - 09/14/19


  • Electrical/Mechanical Rough-in for Veh Storage
  • Metal Roofing for Maint Bldg
  • Plumbing Fixtures for Admin Bldg
  • Cont. Roof on Veh Storage Bldg
  • Steel Framing for Maint Bldg

(For Additional project info and picture updates, click on the following links.)

  1. 190824 Wkly Construction Status Report - Molokai Baseyard
  2. 190810 Wkly Construction Status Report - Molokai Baseyard
  3. 190803 Wkly Construction Status Report - Molokai Baseyard
  4. 190727 Wkly Construction Status Report - Molokai Baseyard
  5. 190720 Wkly Construction Status Report - Molokai Baseyard
  6. 190714 Wkly Construction Status Report - Molokai Baseyard
  7. 190707 Wkly Construction Status Report - Molokai Baseyard
  8. 190630 Wkly Construction Status Report - Molokai Baseyard
  9. 190623 Wkly Construction Status Report - Molokai Baseyard
  10. 190616 Wkly Construction Status Report - Molokai Baseyard
  11. 190609 Wkly Construction Status Report - Molokai Baseyard
  12. 190512 Wkly Construction Status Report - Molokai Baseyard
  13. 190505 Wkly Construction Status Report - Molokai Baseyard
  14. 190428 Wkly Construction Status Report - Molokai Baseyard
  15. 190421 Wkly Construction Status Report - Molokai Baseyard
  16. 190414 Wkly Construction Status Report - Molokai Baseyard
  17. 190407 Wkly Construction Status Report - Molokai Baseyard
  18. 190331 Wkly Construction Status Report - Molokai Baseyard
  19. 190324 Wkly Construction Status Report - Molokai Baseyard
  20. 190317 Wkly Construction Status Report - Molokai Baseyard
  21. 190310 Wkly Construction Status Report - Molokai Baseyard
  22. 190303 Baseyard Wkly Construction Status Report - Molokai
  23. 190224 Wkly Construction Status Report - Molokai Baseyard
  24. 190217 Wkly Construction Status Report - Molokai Baseyard
  25. 190203 Wkly Construction Status Report - Molokai Baseyard
  26. 190127 Wkly Construction Status Report - Molokai Baseyard
  27. 190113 Wkly Construction Status Report - Molokai Baseyard
  28. 180831 Wkly Construction Status Report - Molokai Baseyard
  29. 180827 Wkly Construction Status Report - Molokai Baseyard
  30. 180816 Wkly Construction Status Report - Molokai Baseyard
  31. 180720 Wkly Construction Status Report - Molokai Baseyard
  32. 180706 Wkly Construction Status Report - Molokai Baseyard
  33. 180629 Wkly Construction Status Report - Molokai Baseyard
  34. 180615 Wkly Construction Status Report - Molokai Baseyard
  35. 180608 Wkly Construction Status Report - Molokai Baseyard
  36. 180601 Wkly Construction Status Report - Molokai Baseyard
  37. 190831 Wkly Construction Status Report - Molokai Baseyard
  38. 190907 Wkly Construction Status Report - Molokai Baseyard