Haleakala Highway and Makawao Avenue Improvements

Project Name


Haleakala Highway and Makawao Avenue Improvements
Job No. 14-55


Scope of Work


This project includes 1,000 LF of roadway widening and repaving along Makawao Avenue between Apana Road and Haleakala Highway. The scope of work includes removal of obstructions, relocation of utility poles, relocation of existing fire hydrants, grading, new roadway pavement structure, new AC curbs, concrete curb, pavement striping, traffic sign installation, traffic signal modifications, grass swales, and other incidental items.
(Project Map)


When


Notice to Proceed:  October 22, 2018 
Contract working days: 80
Anticipated Completion Date:  February 19, 2019 
Revised Completed Date:  May 10, 2019


Streets Involved


Makawao Avenue (Between Apana Road and Haleakala Highway)


Contractor


Maui Kupono Builders, LLC
309 Kamalei Circle
Kahului, HI 96732
 


Contract Cost


 $1,050,417.73
 

Project Contact


County of Maui
Department of Public Works
Engineering Division 
(808) 270-7745

Construction Update:

Work Completed Week of 09/01/19 - 09/07/19:


  • Clearing & Grubbing
  • Staking
  • BMP's

Work Scheduled Week of 09/08/19 - 09/14/19:


  • Grading & Prepping for New Utillity Poles



(For additional project info and picture updates, click on the following links.)