Kokomo Road and Makawao Avenue Pavement Reconstruction

Project Name


Kokomo Road And Makawao Avenue Pavement Reconstruction
Job No. STP-0900(086)


Scope of Work


This project involves the reconstruction of Kokomo Road, from Haiku Road to Mile Post 3.0, and Makawao Avenue, from Kokomo Road to Piiholo Road.  Also include on Makawao Ave, will be sidewalk and curb construction, drainage and guardrail improvements, and stone wall reconstruction on Makawao Avenue, and driveway apron improvements. 

PLEASE ANTICIPATE ROAD CLOSURES EACH SATURDAY, FROM 7:00AM - 6:00PM, WEATHER PERMITTING.  DURING THE WEEK, PLEASE ALSO ANTICIPATE SINGLE LANE CLOSURES BETWEEN 8:30AM - 3:00PM.


(Project Map)


When


NTP: February 2, 2018
Contract working days: 178
Anticipated Completion Date:  October 19, 2018

Streets Involved


Kokomo Road (Haiku Road to Mile Post 3.0)
Makawao Avenue (Intersection of Kokomo Road and Makawao Avenue to Piiholo Road)

Contractor


HI-Built
72 Ting’s Drive
Wailuku, Hawaii 96793

Contract Cost


 $4,546,797.82
 

Project Contact


County of Maui,
Department of Public Works
Engineering Division
(808) 270-7745

Work Completed Week of 8/19/18 - 8/25/18:


  • Poured Sidewalk on Makawao Ave

Work Scheduled Week of 8/26/18 - 9/01/18:

  • Continue Sidewalk at Makawao
  • Begin Paving of Makawao Ave at Kokomo Rd
  • Reconstruction on Kokomo Rd at Cannery Mall - ROAD CLOSED 9/1 Weather Pending