Haiku District Resurfacing (FY 2017/2018)

Project Name


Haiku District Resurfacing (FY 2017/2018)
Job No. 17-18


Scope of Work


The project involves cold planing and resurfacing of Peahi Road (Hana Highway to approximately 1.2 miles south) and Pauwela Road, adjusting water valves; replacing speed humps; pavement striping and markers; and other incidental items.
Hours of work (operation/closures) will be from 8:30 a.m. to 3:00 p.m. Monday thru Friday, except weekends and holidays. 
(Project Map)

When


Notice to Proceed:  January 9, 2019
Contract working days: 60
Anticipated Completion Date:  April 5, 2019

Streets Involved


Peahi Road (Hana Highway to approximately 1.2 miles south)
Pauwela Road (Hana Highway to Haiku Road)

Contractor


Maui Paving, LLC
P.O. Box 78
Honolulu, HI 96810

Contract Cost


$600,500.00

Project Contact


DPW Engineering Division (808) 270-7745