Paia School Frontage/Sidewalk Improvements

Project Name


Paia School Frontage/Sidewalk Improvements Safe Routes to School Project
FAP No. SRS-0900(091)


Scope of Work


The project includes concrete sidewalk installation and replacement along Baldwin Avenue between Paia School and Paia Gym and other incidental work necessary to complete the project.
(Project Map)

When


NTP: March 11, 2019
Contract Working Days: 100
Completion Date: Mid June 2019


Streets Involved


Baldwin Avenue (Between Paia School and Paia Gym)

Contractor


West Maui Construction
305 E. Wakea Ave., Ste. 100
Kahului, HI 96732


Contract Cost


$1,066,769.18


Project Contact


Department of Public Works
200 South High Street Suite 410
Engineering Division
(808) 270-7745