Scope of Work


This project consists of the removal of existing pavement down to the gravel subbase within the road right-of-way, and installing a new asphalt concrete pavement section with reinforcing geogrid. The scope of work also includes installing new pavement striping and markers, replacement of existing water system, adjusting manhole/valves frames and covers where needed, removal/replacement of dented guardrails and removing/replacing signage and posts.

 The hours of operation will be from 8:30 am to 3:30 pm Monday to Friday with one lane alternating traffic, and an anticipated weekend full road closure starting in early December.  Weekend hours will be from 7:00 am Saturday until 6:00 pm Sunday with detour route in place.  There will be no activities on holidays.

 For any questions, please call our Engineering Office at 270-7745 
(Project Map)


When


NTP:  October 5, 2020
Contract Working Days: 304
Estimated Completion Date:  May 2021


Streets Involved


Kaupakalua Road (E. Kuiaha Road to Hana Highway)

Contractor


Maui Paving, LLC
949 Kamokila Blvd., Suite 100
Kapolei, HI 96707
(808) 674-8383

Contract Cost


$5,718,862.80


Project Contact


Department of Public Works
200 South High Street Suite 410
Engineering Division
(808) 270-7745

Construction Update:



Work Completed Last Week of 03/22/21 - 03/27/21:


  • Re-Pave ACB from Sta. 199+00 to 200+00 (Bridge section)
  • Pave Mix V from Sta. 187+50 to 237+00 (Pakanu St. to Nolu Rd)
  • No work scheduled for Friday, March 26 State and County Holiday - Prince Jonah Kuhio Kalanianaole Day.
  • Saturday, March 27 Full Road Closure between E. Kuiaha Rd to U. Ulumanu Rd. (5 corners) from 8:00 AM to 4:00 PM.  Road closed to thru traffic.  Detours will be in-place.
  • Roadway reconstruction and ACB paving Sta. 173+00 to 178+00. (Hana side of Lepo St. to Pakanu St.)

Work Scheduled Week of 03/29/21 - 04/02/21:

  • No work scheduled for Friday, April 2 State and County Holiday - Good Friday.
  • Misc. utility adjustments (Btw Peahi Rd and S. Holokai Rd)
  • Pave Mix V from Sta. 237+00 to 278+78 (Nolu Rd to End)
  • Pave Mix V Sta. 173+00 to 178+00 (Hana side of Lepo St. to Pakanu St.)