Project No. 18-41


Scope of Work


The project involves clearing of debris along the bridge railings and unclogging of deck drains; cold-planing & replacing the pavement section over the bridge deck; and repair of deteriorated concrete of the bridge deck, arch rib, arch columns, and other supporting members. Any bridge repairs shall be undertaken in-kind and in accordance with the Secretary of the Interior’s Standards for the Treatment of Historic Properties.
Hours of operation will be from 8:30 am to 3:00 pm Monday to Friday except weekends and holidays for activities occurring under the bridge.  Work on the bridge deck which requires complete road closure will be from 8:00 pm to 4:00 am, Sunday night to Friday morning except weekends and holidays.  Road closure is anticipated to last for a duration of two weeks sometime in early August.
(Project Map)

When


NTP:  June 1, 2021
Contract Working Days: 60
Estimated Completion Date: Late August, 2021

Streets Involved


Hana Hwy.

Contractor


West Maui Construction LLC
305 E Wakea Ave. Ste 100
Kahului, HI 96732
(808) 877-4202

Contract Cost


$1,309,420.00