Kahana Nui Bridge Replacement

Project Name


Kahana Nui Bridge Replacement
FAP No. BR-3080(009)


Scope of Work


The project includes demolition and removal of existing bridge structure footing and abutment walls, existing utilities, landscaping, and concrete curb and gutter, sidewalk and driveways; construction of new asphalt concrete pavement, new concrete gutter, utility improvements, new bridge structure, footing and abutment walls, driveways, sidewalk and curb ramps, signing and striping; and all other incidental work necessary to complete project.

Work days are from Monday to Friday except weekends and holidays. Hours of operation will be from 8:30 am to 3:30 p.1. Single lane closure is anticipated throughout the project duration with some intermittent full road closures as the need arises.
(Project Map)

When


NTP:  February 8, 2022
Contract Working Days: 270
Estimated Completed Date:  Tentative - March 2023

Streets Involved


Lower Honoapiilani Road (between Hua Nui Place and Omaikai Place)

Contractor


Goodfellow Bros. LLC
1300 N. Holopono Street, Suite 201
Kihei, HI 96753
(808) 879-5205

Contract Cost


$5,323,615.90

Project Contact


Department of Public Works
200 South High Street Suite 410
Engineering Division
(808) 270-7745

Construction Update:



Work Completed Last Week:  (06/27/22 to 07/01/22)

  • No field work occurred.
  • Bridge closure notices sent out to EMS, Fire, Police, Maui Bus, School Bus and residents.

Work Scheduled This Week:  (07/04/22 - 07/08/22)


  • No work on Monday 7/4 for Independence Day Holiday.
  • Install detour traffic control signs along Honoapiilani Highway.
  • Bridge closure and detour scheduled for July 5 following installation of detour signage.
  • Continue utility installation within Lower Honoapiilani Road.

Additional Notes


  • Full bridge closure from 7/5/22 through 1/27/23.
  • Water quality in stream monitored daily and photographs taken weekly.