Makamakaole Bridge Guardrail Repairs

Project Name

Makamakaole Bridge Guardrail Repairs

Project No. 20-13                                            

 

Scope of Work

The project involves, but is not limited to, replacing both the upstream and downstream guardrails of the existing Makamakaole Bridge #63, repairing bridge deck spall, replacing joint sealants, and temporary traffic control.

(Project Map)

The week of 3/22/2021, road closure will be implemented with work hours from 9:00 pm to 5:00 am. From the week of 3/29/2021 moving forward, work days are from Monday to Friday except weekends.and holidays. Hours of operation will be from 8:30 am to 3:30 pm. Single lane closure is anticipated throughout the remainder of the project.

For any questions, please call our Engineering Office 270-7145.

When

NTP:  March 22, 2021

Contract Working Days:   60

Estimated Completion Date:   Mid June 2021

 

Streets Involved

Makamakaole Bridge (Kahekili Hwy)

 

Contractor

Global Specialty Contractors, Inc.

94-978 Pakela Street

Waipahu, HI 96797

(808) 843-8881

 

Contract Cost

$100,930.00

 

Project Contact

Department of Public Works
200 South High Street Suite 410
Engineering Division
 (808) 270-7745