- Home
- Government
- Public Works
- Engineering Division
- Current & Future Projects
- Mill Street Pavement Reconstruction
Mill Street Pavement Reconstruction
Project Name
Mill Street Pavement Reconstruction
North Market Street to Lower Main Street
FAP No. STP-3840(001)
Scope of Work
The project involves the removal of existing pavement down to gravel subbase within the
roadway right-of-way and installation of new asphalt concrete pavement section with
reinforcing geogrid; removal and widening of existing sidewalks, removal/installation of new curb/gutters, removal/replacement of existing curb ramps and driveway aprons, installation of new pavement striping and markers, adjusting manholes/valves frames and covers where needed, removal/replacement of existing drainlines, removal/replacement of existing catch basins and drain manholes, and removal/replacement of signage and posts. Portion of existing retaining wall along Mill Street will also be removed and replaced with new retaining
wall.
Work days are from Monday to Friday except weekends and holidays with hours of operation from 8:30 am to 3:30 pm. Single lane closure is anticipated throughout the project duration with some intermittent full road closures as the need arises.
When
NTP: February 28, 2022
Contract Working Days: 302
Estimated Completed Date: April 2023
Streets Involved
Mill Street (North Market St. to Lower Main St.)
Contractor
Maui Kupono Builders, LLC dba Manu Builders
309 Kamalei Circle,
Kahului, HI 96732
(808) 870-4789
Contract Cost
$4,101,628.87
Project Contact
Department of Public Works
200 South High Street Suite 410
Engineering Division
(808) 270-7745
Construction Update:
Work Completed Last Week: (06/20/22 to 06/24/22)
- Continue installation of curb & gutter/Sidewalk between Imi Kala St. and Lower Main St.
- Start drainline above Hale Wili St.
Work Scheduled This Week: (06/27/22 to 07/02/22)
- Continue installation of curb & gutter/Sidewalk between Imi Kala St. and Lower Main St.
- Install Wheel Chair Ramps at Imi Kala St.
- Start drainline above Hale Wili St.
Weekend Work Scheduled (Full Road Closure/24Hrs: (06/25/22 to 06/28/22)
- Roadway will be closed from Sat. 6/25 to Tues. 6/28 between Market St. to Central Ave.
- Roadway reconstruction (Saturday 6/25)
- Roadway reconstruction (Sunday 6/26)
- Roadway Base Course and Pavement fabric installation (Monday 6/27)
- Roadway HMA Asphalt Base Course and HMA Mix IV (Tuesday 6/28)
(For additional project info. and picture updates, clink on the following links.)
- 220627 Mill St Pavt Recon Weekly Status Report
- 220620 Mill St Pavt Recon Weekly Status Report
- 220613 Mill St Pavt Recon Weekly Status Report
- 220530 Mill St Pavt Recon Weekly Status Report
- 220523 Mill St Pavt Recon Weekly Status Report
- 220516 Mill St Pavt Recon Weekly Status Report
- 220509 Mill St Pavt Recon Weekly Status Report
- 220502 Mill St Pavt Recon Weekly Status Report
- 220425 Mill St Pavt Recon Weekly Status Report
- 220418 Mill St Pavt Recon Weekly Status Report
- 220411 Mill St Pavt Recon Weekly Status Report
- 220404 Mill St Pavt Recon Weekly Status Report
- 220328 Mill St Pavt Recon Weekly Status Report
- 220321 Mill St Pavt Recon Weekly Status Report
- 220314 Mill St Pavt Recon Weekly Status Report
- 220307 Mill St Pavt Recon Weekly Status Report