Scope of Work

The scope of work for this project involve installing a concrete pavement section to replace the damaged asphalt concrete pavement; installing GRP slopes to repair the eroded shoulders; replacing guardrails; repairing undermining at the CRM abutments and wingwalls of the existing bridge culvert; replacing a barbed wire fence; installing pavement markings and signage; and other incidental work.

(Project Map)

 

When

NTP:  TBD

Contract Working Days:   60

Estimated Completion Date:   TBD

 

Streets Involved

Awalau Road

 

Contractor

Goodfellow Bros. LLC

1300 N. Holopono Street, Ste 101

Kihei, HI 96753

(808) 879-5205

 

Contract Cost

$1,054,888.00

 

Project Contact

Department of Public Works
 200 South High Street Suite 410
 Engineering Division 
 (808) 270-7745