Pavement Reconstruction of Kalae Roads & Resurfacing of Airport Loop Road

Project Name

Pavement Reconstruction of Kalae Roads & Resurfacing of Airport Loop Road

Project No. 22-35

 

Scope of Work

The project involves the reconstructing the pavement of various roads in Kalae and resurfacing of the Airport Loop Road in Hoolehua.  The scope of work also involves pavement striping and markers; adjustment of manholes and water valves; installation of signs; and other incidental items.

(Project Map)

 

When

NTP:  TBD

Contract Working Days:   120

Estimated Completed Date:   TBD

 

Streets Involved

-Airport Loop Road

-Akeu Way

-Koala Way

-Nanikai Place

 

Contractor

Maui Paving, LLC

1300 N. Holopono St., Suite 201

Kihei, HI 96753

(808) 877-2755

 

Contract Cost

$1,168,526.25

 

Project Contact

Department of Public Works
 200 South High Street Suite 410
 Engineering Division 
 (808) 270-7745