Project Name
Emergency Slope Repairs at Manawainui Gulch
Project No. 22-43
Scope of Work
The project includes scaling of loose rocks from the slope and disposal of the same, removal and disposal of debris, repair of existing wire mesh, replacement of guardrail and other incidental items. Rock scaling and debris removal activities which requires complete road closure from 8:00am to 5:00 pm will begin on Saturday, July 16, 2022 with anticipated completion on
Tuesday July 19, 2022. Remaining activities not requiring road closure will continue for additional three weeks.
For any questions, please call our Engineering Office at 270-7745.
(Project Map)
When
NTP: July 16, 2022 (Start of Construction)
Contract Working Days: 20
Estimated Completion Date: August 12, 2022
Streets Involved
Piilani Highway (Near Manawainui Gulch)
Contractor
Prometheus Construction
651 Komohana St.
Kapolei, HI 96707
(808) 591-1143
Contract Cost
$239,084.00
Project Contact
Department of Public Works
200 South High Street Suite 410
Engineering Division
(808) 270-7745