Scope of Work

The project involves resurfacing of various pavement sections in Paia, Haiku, and

Kula districts of Maui. The scope of work includes cold planing, road resurfacing,

installation of pavement striping and markers, reconstruction of water valves and manholes, replacement of existing signage, new signage, reconstruction of speed humps, and other incidental items.

(Project Map)

 

Hours of operation will be from 8:30 a.m. to 3:30 p.m. Monday thru Friday except

holidays and weekends.

 

For any questions, please call our Engineering Office at 270-7745.

 

When

NTP:  November 20, 2023

Contract Working Days:   100

Estimated Completion Date:   Ending of April, 2024

 

Streets Involved

Kalia Place (Haiku)

Kekoanui Place (Haiku)

Lia Place (Haiku)

Nanihoku Place (Haiku)

Kamehameiki Place (Kula)

South Holokai Road (Kula)

Apo Place (Paia)

 

Contractor

Maui Paving, LLC

1300 N. Holopono Street, Suite 201

Kihei, HI 96753

(808) 877-2755

 

Contract Cost

$972,845.00

 