Maui Lani Roundabout Project to begin construction Monday, June 15

Mayor Michael Victorino announced that major intersection construction work on the Maui Lani Roundabout project will begin Monday, June 15, 2020.

The intersection of Maui Lani Parkway and Kamehameha Avenue will be fully closed (24 hours a day, 7 days a week) from June 15, 2020, through July 31, 2020.

Detour signs will direct traffic around the work area.

Goodfellow Bros. personnel will be working at the site from 7 a.m. – 4 p.m. daily, except Sundays. Pedestrian and bicycle access will continue to be available, and a plan is currently under review.

“This closure will expedite the construction schedule by two to three months while school is not in session,” Department of Public Works Director Rowena Dagdag-Andaya said. “Doing construction now, also minimizes any major traffic disruptions once schools reopen.”

“We’ll be working with Goodfellow Bros. to make sure they finish construction before our keiki return to school in August,” Mayor Victorino said. “We are excited to see this project moving forward and appreciate the community’s patience and understanding.”


Project details

General contractor: Goodfellow Bros.

Contract amount: $3.15 million

Work began: April 27, 2020

Scope of work: Removal of obstructions, road pavement work, construction of curb ramps and sidewalks, adjusting manholes, installation of irrigation and water valves and a storm drain culvert, replacing street signs and other improvements

For more information, visit the Maui Lani roundabout Facebook page at https://www.facebook.com/Maui-Lani-Roundabout-Page-755419297998298/

# # #

Facebook Twitter Email

Other News in Press Releases

Kokua Pool improvements announced

Posted on: May 5, 2020

Checkpoints for roadways to Hana

Posted on: April 18, 2020