Wailuku Town infrastructure upgrades to begin Monday, Sept. 28, on W. Vineyard Street

DETOUR Map REV 9-25-20

Road improvements on W. Vineyard St. between Market St. and Church St. will begin on Monday, Sept. 28, as part of Phase 1A of the Wailuku Town Improvements project, according to the County of Maui, Department of Management.

 Crews from MIRA Image Construction, LLC will be working from 8:30 a.m. to 3:30 p.m., Monday through Friday. Work is slated for completion January 2021.

W. Vineyard Street will be one-way traveling westbound in the construction area between Market Street and Church Street. Motorists should also observe all detour signage while driving in the area.

The municipal parking lot will remain open during construction; however, the only entrance to the parking lot will be from Market St., and the only exits will be at Market and Church Streets.

Traffic Control Guards and/or signage will be stationed at intersections to assist with guiding traffic around the construction zone.

“This construction on Vineyard St. will include much-needed upgrades for this area,” Mayor Michael Victorino said. “These improvements will serve residents and businesses by providing quality roads, water and sewer lines, and drainage systems. Sidewalks will also be improved to ensure safety and walkability for pedestrians that frequent our local Wailuku businesses. We appreciate everyone’s patience during this time.”

For questions or concerns regarding the road improvement projects, contact MIRA Image Construction LLC’s Superintendent David Perez (808) 306-5206.

For the latest updates on the Wailuku Town Improvement projects, visit www.WailukuLIVE.com.

###

(PLEASE SEE MAP FOR WORK AREA AND DETOUR ROUTES)

Facebook Twitter Email

Other News in Press Releases

DMVL Lahaina Office closed today, Sept. 18

Posted on: September 18, 2020

Kokua Pool improvements announced

Posted on: May 5, 2020

Checkpoints for roadways to Hana

Posted on: April 18, 2020